Concrete Pouring is More Than 60% Complete

Package 1 Construction 2 2.20.24

Work on the AWP Program is progressing with more than 60% of the concrete poured for the structures and buildings at the main site located north of Santee Lakes.

As of February 2024, roughly 32,000+ cubic yards of concrete has allowed portions of the advanced water purification, water recycling and solids handling facilities to take shape. 

Once complete, 52,400 cubic yards of concrete will be poured- enough to fill 16 Olympic-sized swimming pools.


Facebook Twitter Email

Other News in Home

Santee Lakes Construction 2 2.20.24

Santee Lakes: Notice of Temporary Road Closure

Posted on: February 23, 2024 | Last Modified on: March 31, 2014
Energy Recovery System

How We’ll Turn Organic Waste Into Energy

Posted on: February 13, 2024
East County AWP Animal

Breeding Season Begins

Posted on: February 5, 2024
Hydrostatic testing

HDD Pipeline Testing is Almost Complete

Posted on: February 5, 2024
Strathmore Drive Parking

Video: Stowe Trail Access

Posted on: February 5, 2024
AWP Construction Site

That's a Wrap: 2023 End of the Year Update

Posted on: February 5, 2024 | Last Modified on: March 31, 2014
Pipeline Fusing

Pipeline Fusing is Complete

Posted on: February 5, 2024
Tertiary Filer Complex

Concrete Pours Before Sunrise

Posted on: February 5, 2024
Construction Underway on East County AWP Program

Why do Some AWP Structures Have Water?

Posted on: February 5, 2024
New Sign on Birchcrest

Signs Remind Visitors Where to Park for Stowe Trail

Posted on: February 5, 2024 | Last Modified on: March 31, 2014
AWP Visitor's Center Timelapse Shot

Timelapse Footage Captures Construction Progress

Posted on: February 7, 2024 | Last Modified on: March 31, 2014
Photo of Package 2

East County AWP Program is Awarded $2 Million Grant from San Diego River Conservancy