HDD Pipeline Testing is Almost Complete

Hydrostatic testing

Testing is nearly complete on the three different horizontal directional drill wastewater pipelines.

In mid-December of 2023, the 18-inch high density polyethylene (HDPE) plastic pipeline underwent hydrostatic testing. This is a pressure test using water to analyze the durability of the pipe as well as the quality of the welded joints. During the test, pressure was held for one hour while the team checked there was no leakage over a three hour period. The water for the testing was used from Santee Lakes and later returned to the lake to avoid waste. 

The 8-inch pipeline that was fused together late last year has since undergone air testing. The final HDD component to be tested is the 36-inch pipeline with that slated to happen within the next few months.

The testing of these pipelines is a requirement before moving on to the next step of construction.

Facebook Twitter Email

Other News in Home

Santee Lakes Construction 2 2.20.24

Santee Lakes: Notice of Temporary Road Closure

Posted on: February 23, 2024 | Last Modified on: March 31, 2014
Energy Recovery System

How We’ll Turn Organic Waste Into Energy

Posted on: February 13, 2024
East County AWP Animal

Breeding Season Begins

Posted on: February 5, 2024
Strathmore Drive Parking

Video: Stowe Trail Access

Posted on: February 5, 2024
AWP Construction Site

That's a Wrap: 2023 End of the Year Update

Posted on: February 5, 2024 | Last Modified on: March 31, 2014
Package 1 Construction 2 2.20.24

Concrete Pouring is More Than 60% Complete

Posted on: February 23, 2024
Pipeline Fusing

Pipeline Fusing is Complete

Posted on: February 5, 2024
Tertiary Filer Complex

Concrete Pours Before Sunrise

Posted on: February 5, 2024
Construction Underway on East County AWP Program

Why do Some AWP Structures Have Water?

Posted on: February 5, 2024
New Sign on Birchcrest

Signs Remind Visitors Where to Park for Stowe Trail

Posted on: February 5, 2024 | Last Modified on: March 31, 2014
AWP Visitor's Center Timelapse Shot

Timelapse Footage Captures Construction Progress

Posted on: February 7, 2024 | Last Modified on: March 31, 2014
Photo of Package 2

East County AWP Program is Awarded $2 Million Grant from San Diego River Conservancy

Posted on: February 5, 2024 | Last Modified on: March 31, 2014